Construction Update: Week 28

We're so close we can almost taste it.  We've got some major updates this week.  Foremost, the large brewhouse is on site and we have a couple of our medium tanks.  The first absolutely gorgeous piece of backbar cabinetry was installed, which allowed us to put the draft system together.  We also put some amenities in the fully functional bathrooms (like TP holders and mirrors...).  Have you noticed the lettering going up on the exterior yet?  New trap door above cooler, fresh paint on previously unpainted surfaces and lots more.  It's starting to look like a brewery around here!

Construction Update: Week 25

Things are really starting to shape up over at The Owl.  We erected our pallet racking and Joe decided to show it off.  The bar is coming along nicely, and it's stunning.  The HVAC guys are doing the last of the work necessary to get the AC turned on, the electricians are getting lights and fans rigged up in the bathrooms, the painters are touching up a few finish items, and the concrete guys are prepping to pour the beer garden slab early next week!!  SQUEEE!! 

Construction Update: Week 24

Yet another week of awesome at The Owl.  We received our kegs this week.  There's a lot of them.  Just ask Joe, he moved them all upstairs.  The painters spent the week touching up and sealing some of the floor they didn't get last week, like inside the cooler.  The electricians started hanging lights downstairs.  We've got all our production lighting and some of the taproom lighting in place.  We also got our glassware and our mill this week.  Cheers!

Construction Update: Week 22

We've been busy this week.  If you haven't driven by the brewery lately, you might think about taking a ride.  The painters did a beautiful job repainting the exterior of the building.  We also took the old blade sign down this week and sent it off to be refurbished.  No worries, it'll be back in a few weeks looking brand new.  As if that wasn't enough, we also have interior doors, drop ceiling frame in the bathrooms, bathroom partitions are in the building and waiting to be installed, the cooler is cooling, and our 1bbl pilot system has arrived. 

Construction Update: Week 20

There is a lot going on these days.  But it's going to be hard to show it all to you this week because the building is wrapped up like some kind of holiday gift.  The painters have everything covered as they prime the ceiling and get ready to paint.  We had the grinder give the floor a once over as we prepare to seal it as well.  Oh!  And we have runners on our stairs now!  After 20 weeks, it's amazing how excited we are about stairs...