Construction Update: Week 15

Rock'n and Rollin' this week.  Our glycol system arrived on Friday and is ready to go up on the roof next week.  We've also got walls!  The drywall is nearly complete, which makes it that much easier to envision the final space.  The lights upstairs are installed and functional.  The new water main has been run from the street into the building.  That means we should get our sprinkler system installed pretty soon.  We've also cut a curb into the roof of the second floor as we prepare for the freight lift install next week.  Big things are happening...